| Author |
2002 sequential convoy
|
|
| Richard 2005-07-07, 2:48 am |
| I need to be able to concatinate an (unknown) number of messages in a 2002
orchestration. In 2004 I would use a sequential convoy with a timeout but I
have never used 2002 orchestrations. Does anyone have an example of something
siumilar in their archives ?
| |
| Stephen W. Thomas 2005-07-07, 5:52 pm |
| Hello.
It has been a very long time… but as far as I know it is not possible to do
a message convoy in BizTalk 2002.
Stephen W. Thomas
http://www.biztalkgurus.com
"Richard" wrote:
> I need to be able to concatinate an (unknown) number of messages in a 2002
> orchestration. In 2004 I would use a sequential convoy with a timeout but I
> have never used 2002 orchestrations. Does anyone have an example of something
> siumilar in their archives ?
| |
| Tom Lysholt Hansen 2005-07-07, 5:52 pm |
| Stephen is right.
Convoys are not supported in BTS2002 at all. It's a new feature to BTS2004.
--
Regards
Tom Lysholt Hansen
"Stephen W. Thomas" wrote:
[vbcol=seagreen]
> Hello.
>
> It has been a very long time… but as far as I know it is not possible to do
> a message convoy in BizTalk 2002.
>
> Stephen W. Thomas
> http://www.biztalkgurus.com
>
>
> "Richard" wrote:
>
|
|
|
|