07-22-04 10:56 PM
I dont think there is any way to know the number of parallel branches at
runtime. Also you cannot add a parallel brach at runtime.
What scenario are you looking to achieve?
--------------------
| >>MIME-Version: 1.0
| >>Content-Type: text/plain; charset=us-ascii
| >>From: culker<can_ulker@hotmail.com>
| >>Message-ID: < 7432003a23994dcda5662a8786f0ab8a@biztalk
ug>
| >>Subject: Parallel Actions Shape related issue
| >>Date: Wed, 21 Jul 2004 11:50:04 GMT
| >>Newsgroups: microsoft.public.biztalk.orchestration
| >>NNTP-Posting-Host: ool-435531cd.dyn.optonline.net 67.85.49.205
| >>Lines: 1
| >>Path:
cpmsftngxa06.phx.gbl!TK2MSFTNGXA01.phx.gbl!TK2MSFTNGP08.phx.gbl!TK2MSFTNGP10
.phx.gbl
| >>Xref: cpmsftngxa06.phx.gbl microsoft.public.biztalk.orchestration:7239
| >>X-Tomcat-NG: microsoft.public.biztalk.orchestration
| >>
| >>Hi,
| >>
| >>Is there anyway to determine the number of parallel branches in a
Parallel Action shape at runtime in BTS04.
| >>
| >>I have a need to process n number of actions in parallel and I will
only know the number of parallel branches at runtime.
| >>
| >>Any ideas, or guidance on this is grately appreciated.
| >>
| >>Thanks,
| >>culker
| >>
| >>
| >>----------------------------------------------
| >>sent via http://www.biztalkug.com
| >>all about BizTalk
| >>
This posting is provided "AS IS" with no warranties, and confers no rights.
EBusiness Server Team
[ Post a follow-up to this message ]
|